Wing A - Above terrace works – Waterproofing work in progress
Above terrace work- OHT , service shaft works in progress
Nov 2025

DRAG
Wing B - Parapet work in progress
Nov 2025
Wing C - Above terrace work | Over Head Tank and waterproofing WIP
Nov 2025
Tiling works Wing A B C - flooring work in progress
Nov 2025
Painting works Wing A, B and C | painting work is underway
Nov 2025
UPVC windows, doors installation work in progress
Nov 2025
Basement | flooring ,painting and Services work in progress
Nov 2025
Podium waterproofing work in progress
Nov 2025
Staircase railing work in progress
Nov 2025
Corridor Tiling and Painting work in progress
Nov 2025
Fire and Plumbing shafts painting work in progress
Nov 2025
Above terrace structural work in progress
Nov 2025
Wing B - Milestone Release - On Commencement Installation of Lift - Status as on 26th Nov 2025
Nov 2025
Wing A - Work in progress above terrace area
Oct 2025
Wing B - Terrace structure work in progress
Oct 2025
Wing C - Above terrace work in progress
Oct 2025
Tiling work is underway across all the Blocks
Oct 2025
Painting work in progress across all the Blocks
Oct 2025
Windows and doors installation work is underway
Oct 2025
Basement flooring & painting work in progress.
Oct 2025
Podium waterproofing work in progress
Oct 2025
Staircase railing work in progress
Oct 2025
Corridor Tiling and Painting work in progress
Oct 2025
Fire and Plumbing shafts painting work in progress
Oct 2025
Above terrace structural work in progress
Oct 2025
Wing A - Milestone Release - On Commencement of Painting- 14th to 21st Floor - Status as on 27th Oct 2025
Oct 2025
Wing B - Milestone Release - On Commencement of Painting- 14th to 21st Floor - Status as on 27th Oct 2025
Oct 2025
Wing C - Milestone Release - On Commencement of Painting- 14th to 21st Floor - Status as on 27th Oct 2025
Oct 2025
Wing A - Terrace slab completed for part of the slab. Parapet wall and external wall putty work is underway above Terrace work for part of the slab
Sep 2025
Wing B - Terrace slab completed for part of the slab
Sep 2025
Wing C - Terrace slab completed for part of the slab Parapet wall work in progress.
Sep 2025
Non tower Area - Waterproofing work in progress.
Sep 2025
Wing A , B and C - Flooring work in progress
Sep 2025
Wing A, B and C - Painting work in progress
Sep 2025