Aurum Wing A
Jun 2025

DRAG
Aurum Wing B
Jun 2025
Aurum Wing C
Jun 2025
Non tower Area Planter wall concrete work in progress
Jun 2025
Aurum Tiling works Wings A, B C - 9th floor work in progress
Jun 2025
Aurum Painting works Wings A, B C - 10th floor work in progress
Jun 2025
Aurum Passenger lift installation work in progress
Jun 2025
Aurum UPVC windows, doors installation work in progress 1st floor
Jun 2025
Aurum Basement painting work in progress
Jun 2025
Brigade EL Dorado Aurum Wing C - Milestone Release On Casting of Sixteenth Floor Slab
Jun 2025
Brigade EL Dorado Aurum Wings A, B, C
Jun 2025
Brigade EL Dorado Aurum Wings A, B, C
Jun 2025
Brigade EL Dorado Aurum Wings A, B, C
Jun 2025
Aurum Wing B – Milestone Release On Casting of Sixteenth Floor Slab
Jun 2025
Wing C – Milestone Release On Commencement Installation of Lift
Jun 2025
Wing C – Milestone Release On Commencement Installation of Lift
Jun 2025
Wing A - Pour 1-18th floor wall reinforcement work in progress
May 2025
Wing B - Pour 3-16th floor slab concrete work in progress
May 2025
Wing C - Pour 5-16th floor slab concrete work in progress
May 2025
Non tower Area Planter wall concrete work in progress
May 2025
Tiling works – 131/477. Wings A, B & C - 7th floor work in progress
May 2025
Painting works – 156/477 (upto putty). Wings A, B & C - 8th floor work in progress
May 2025
Basement painting and DWG work in progress
May 2025
Wing A – Milestone Release On Casting of Sixteenth Floor Slab
May 2025
Wing A – Milestone Release On Commencement of Flooring 7 to 13 Floor
May 2025
Wing B – Milestone Release On Commencement of Flooring 7 to 13 Floor
May 2025
Wing C – Milestone Release On Commencement of Flooring 7 to 13 Floor
May 2025
Front elevation
Apr 2025
Wing A
Apr 2025
Wing B
Apr 2025
Wing C
Apr 2025
Non tower Area -Podium planter box work in progress
Apr 2025
Tiling works. Wing A - 6th floor work in progress. Wing B - 6th floor work in progress. Wing C - 6th floor work in progress
Apr 2025
Painting works. Wing A - 8th floor work in progress. Wing B - 7th floor work in progress. Wing C - 7th floor work in progress
Apr 2025
OWC slab concreting completed, retaining wall work in progress
Apr 2025
Basement work in progress
Apr 2025
Wing C – Milestone Release On Casting of 12th Floor Slab
Apr 2025