Terrace painting work in progress
Sep 2026

DRAG
Terrace clay tile work completed
Sep 2026
Corridor Tiling work completed
Sep 2026
Corridor Tiling work completed
Sep 2026
Staircase railing work completed
Sep 2026
Podium Hardscape and softscape work in progress
Sep 2026
Basement- Services work in progress
Sep 2026
Basement- Services work in progress
Sep 2026
Internal certification in progress
Sep 2026
Internal certification in progress
Sep 2026
UPVC windows, doors installation work in progress
Sep 2026
UPVC windows, doors installation work in progress
Sep 2026
Painting work in progress
Sep 2026
Tiling works – completed
Sep 2026
External painting work in progress
Sep 2026
External painting work in progress
Sep 2026
Wing C
Sep 2026
Wing B
Sep 2026
Wing A
Sep 2026
External painting work in progress
Sep 2026
External painting work in progress
Aug 2026
Wing A
Aug 2026
Wing B
Aug 2026
Wing C
Aug 2026
External painting work in progress
Aug 2026
Tiling works – completed
Aug 2026
Painting work in progress
Aug 2026
UPVC windows, doors installation work in progress
Aug 2026
Internal certification of units
Aug 2026
Basement - VDF flooring ,painting and Services work in progress
Aug 2026
Podium Hardscape and softscape work in progress
Aug 2026
West side driveway work completed
Aug 2026
Staircase railing work completed
Aug 2026
Corridor Tiling and Painting work completed
Aug 2026
Terrace clay tile work in progress
Aug 2026
Terrace painting work in progress
Aug 2026