Front elevation
Mar 2025

DRAG
Wing A
Mar 2025
Wing B
Mar 2025
Wing C
Mar 2025
Non tower Area -Podium planter box work in progress
Mar 2025
Tiling works
Mar 2025
Painting works
Apr 2025
OWC slab concreting completed, retaining wall work in progress
Apr 2025
Basement work in progress
Apr 2025
Wings A, B & C – Milestone Release On Commencement of Painting 7 to 13 Floor
Mar 2025
Wings A, B & C – Milestone Release On Commencement of Painting 7 to 13 Floor
Mar 2025
Wings A, B & C – Milestone Release On Commencement of Painting 7 to 13 Floor
Mar 2025
Wing B – Milestone Release On Casting of 12th Floor Slab
Mar 2025
Wing A – Milestone Release On Casting of 12th Floor Slab
Mar 2025
Wing A - Pour 1 - 13th floor wall reinforcement work in progress. Pour 2 - 11th floor wall reinforcement work in progress
Feb 2025
Wing B - Pour 3 - 11th floor wall reinforcement work in progress. Pour 4 - 11th floor wall reinforcement work in progress
Feb 2025
Wing C - Pour 5 - 9th floor wall reinforcement work in progress. Pour 6 - 12th floor wall shuttering work in progress
Feb 2025
Non tower Area Podium area structure work in progress
Feb 2025
Tiling works Wing A - 5th floor work in progress
Wing B - 4th floor work in progress. Wing C - 4th floor work in progress
Feb 2025
Painting works. Wing A - 5th floor work in progress. Wing B - 5th floor work in progress. Wing C - 5th floor work in progress
Feb 2025
OWC slab shuttering and reinforcement, retaining wall work in progress
Feb 2025
Wing C – Milestone Release On Casting of Eighth Floor Slab
Mar 2025
Wing A
Jan 2025
Wing B
Jan 2025
Wing C
Jan 2025
Non tower Area -Podium area structure work in progress
Jan 2025
Tiling work in progress
Jan 2025
Painting work in progress
Jan 2025
Wing B – Milestone Release On Casting of Eighth Floor Slab
Jan 2025
Wing B – Milestone Release On Commencement of Painting 1 to 6 Floor
Jan 2025
Wing A – Milestone Release On Casting of Eighth Floor Slab
Jan 2025
Wing C – Milestone Release On Casting of Fourth Floor Slab and Flooring 1 to 6 Floor
Dec 2024
Wing C – Milestone Release On Casting of Fourth Floor Slab and Flooring 1 to 6 Floor
Dec 2024