Wing A - Pour 1 - 5th Floor Slab Reinforcement Work in Progress
Aug 2024
DRAG
Wing B - Pour 3 - 3rd Floor Slab Reinforcement Work in Progress and Pour 4 - 2nd Floor Slab Shuttering Work in Progress.
Aug 2024
Wing C – Pour 5 - 2nd Floor Wall Shuttering Work in Progress and Pour 6 - 2nd Floor Wall and Slab Shuttering Work in Progress.
Aug 2024
Non tower area - STP structural work completed. Podium area structure work in progress
Aug 2024
Wing A – Milestone Release On Casting of Fourth Floor Slab
Aug 2024
Wing A - Second floor slab work in progress. Wing B - Second floor wall reinforcement work in progress. Wing C - First floor slab shuttering work in progress
Jun 2024
STP basement floor to Ground floor Column reinforcement wip
Jun 2024