Wing A - Above Terrace - Waterproofing, OHT, Service Shaft work in progress
Dec 2025

DRAG
Wing B
Dec 2025
Wing C - Above terrace work - Service shaft, and waterproofing work in progress
Dec 2025
External painting work in progress
Dec 2025
Tiling works Wing A B C | Flooring work in progress
Dec 2025
Wing A B C Painting work in progress
Dec 2025
UPVC windows, doors installation work in progress
Dec 2025
QA certification in progress
Dec 2025
Basement- flooring ,painting and Services work in progress
Dec 2025
Podium waterproofing work in progress
Dec 2025
Staircase railing work in progress
Dec 2025
Corridor Tiling & painting work in progress
Dec 2025
Fire and Plumbing shafts painting work in progress
Dec 2025
Above terrace structural work in progress
Dec 2025
Terrace waterproofing work in progress
Dec 2025
Wing A - Milestone Release -"On Commencement of Window fixing-14to21F" - Status as on 29th Dec 2025
Dec 2025
Wing B - Milestone Release -"On Commencement of Window fixing-14to21F" - Status as on 29th Dec 2025
Dec 2025
Wing C - Milestone Release -"On Commencement of Window fixing-14to21F" - Status as on 29th Dec 2025
Dec 2025
Wing A - Above terrace works – Waterproofing work in progress
Above terrace work- OHT , service shaft works in progress
Nov 2025
Wing B - Parapet work in progress
Nov 2025
Wing C - Above terrace work | Over Head Tank and waterproofing WIP
Nov 2025
Tiling works Wing A B C - flooring work in progress
Nov 2025
Painting works Wing A, B and C | painting work is underway
Nov 2025
UPVC windows, doors installation work in progress
Nov 2025
Basement | flooring ,painting and Services work in progress
Nov 2025
Podium waterproofing work in progress
Nov 2025
Staircase railing work in progress
Nov 2025
Corridor Tiling and Painting work in progress
Nov 2025
Fire and Plumbing shafts painting work in progress
Nov 2025
Above terrace structural work in progress
Nov 2025
Wing B - Milestone Release - On Commencement Installation of Lift - Status as on 26th Nov 2025
Nov 2025