Luminaire Front View. External painting Works in progress
Jun 2025

DRAG
Luminaire Wing A - Above terrace level painting work in progress
Jun 2025
Luminaire Wing B - Above Terrace level painting work in progress
Jun 2025
Luminaire Wing C - Above Terrace floor level painting work in progress
Jun 2025
Luminaire Internal flats finishing work in progress
Jun 2025
Luminaire Flooring work in progress
Jun 2025
Luminaire Toilet dado work in progress. Plumbing works completed
Jun 2025
Luminaire Painting (Putty) work in progress
Jun 2025
Luminaire Sanitary fixtures work in progress
Jun 2025
Luminaire Balcony railing work in progress
Jun 2025
Luminaire UPVC doors and windows work in progress
Jun 2025
Luminaire Fixing of doors work in progress
Jun 2025
Luminaire External painting work in progress
Jun 2025
Luminaire Lift installation work in progress
Jun 2025
Luminaire Basement work in progress
Jun 2025
Luminaire Central podium Landscape work in progress
Jun 2025
Luminaire Between L and A tower podium finishing work in progress
Jun 2025
Luminaire Terrace clay tile and painting work in progress
Jun 2025
Front View. Structure Works in progress
Apr 2025
Wing A - Above terrace floor level structural work in progress
Apr 2025
Wing B - Above Terrace level structural work in progress
Apr 2025
Wing C - Above Terrace floor level structural work in progress
Apr 2025
QA Certification – 26/477. Internal flats finishing work in progress
Apr 2025
Flooring – 454/477 work in progress.
Apr 2025
Toilet dado – 465/477 work in progress. Plumbing works completed
Apr 2025
Painting (Putty) – 410/477 work in progress
Apr 2025
Sanitary fixtures – 60/477 work in progress
Apr 2025
Balcony railing – 467/477 work in progress
Apr 2025
UPVC doors and windows – 450/477 work in progress
Apr 2025
Fixing of doors – 440/477 work in progress
Apr 2025
External painting work in progress
Apr 2025
Lift installation work in progress
Apr 2025
Basement work in progress
Apr 2025
Central podium Landscape work in progress
Apr 2025
Between L and A tower podium finishing work in progress
Apr 2025
Terrace clay tile and OHT finishing work in progress
Apr 2025