Front View. Structure Works in progress
Apr 2025

DRAG
Wing A - Above terrace floor level structural work in progress
Apr 2025
Wing B - Above Terrace level structural work in progress
Apr 2025
Wing C - Above Terrace floor level structural work in progress
Apr 2025
QA Certification – 26/477. Internal flats finishing work in progress
Apr 2025
Flooring – 454/477 work in progress.
Apr 2025
Toilet dado – 465/477 work in progress. Plumbing works completed
Apr 2025
Painting (Putty) – 410/477 work in progress
Apr 2025
Sanitary fixtures – 60/477 work in progress
Apr 2025
Balcony railing – 467/477 work in progress
Apr 2025
UPVC doors and windows – 450/477 work in progress
Apr 2025
Fixing of doors – 440/477 work in progress
Apr 2025
External painting work in progress
Apr 2025
Lift installation work in progress
Apr 2025
Basement work in progress
Apr 2025
Central podium Landscape work in progress
Apr 2025
Between L and A tower podium finishing work in progress
Apr 2025
Terrace clay tile and OHT finishing work in progress
Apr 2025
Front View - Structure Works in progress
Mar 2025
Wing A - Above terrace floor level structural work in progress
Mar 2025
Wing B - Above Terrace level structural work in progress
Mar 2025
Wing C - Above Terrace floor level structural work in progress
Mar 2025
Internal flats finishing work in progress
Mar 2025
Flooring – 440/477 work in progress
Mar 2025
Toilet dado – 450/477 work in progress. Plumbing works completed
Mar 2025
Painting (Putty) – 400/477 work in progress
Mar 2025
Sanitary fixtures – 35/477 work in progress
Mar 2025
Balcony railing – 437/477 work in progress
Mar 2025
UPVC doors and windows – 400/477 work in progress
Mar 2025
Fixing of doors – 410/477 work in progress
Mar 2025
External painting work in progress
Mar 2025
Lift installation work in progress
Mar 2025
Basement work in progress
Mar 2025
Central podium Landscape work in progress
Mar 2025
Between L and A tower podium finishing work in progress
Mar 2025
Terrace clay tile and OHT finishing work in progress
Mar 2025
Front View - Structure Works in progress
Feb 2025
Wing A - Above terrace floor level structural work in progress
Feb 2025
Wing B - Above Terrace level structural work in progress
Feb 2025
Wing C - Above Terrace floor level structural work in progress
Feb 2025
Internal flats finishing work in progress
Feb 2025
Flooring work in progress
Feb 2025
Toilet dado and plumbing work in progress
Feb 2025
Putty work in progress
Feb 2025
Sanitary fixtures work in progress
Feb 2025
Balcony flooring and railing work in progress
Feb 2025
UPVC doors and windows work in progress
Feb 2025
Fixing of doors work in progress
Feb 2025
External painting work in progress
Feb 2025
Lift installation work in progress
Feb 2025