Structure & Finishes completed
Nov 2025

DRAG
East Wing
Nov 2025
South Wing
Nov 2025
West Wing
Nov 2025
East ,South and West wing External Painting works completed
Nov 2025
Finishing Work
Nov 2025
Finishing Work
Nov 2025
Corridor Area finishing works
Nov 2025
Emerald
Nov 2025
Ground floor triple height entrance and reception area
Nov 2025
Basement finishes completed
Nov 2025
South & west face road and car parking area works completed
Nov 2025
Podium Central Courtyard Area Hardscape and Softscape work completed
Nov 2025
Podium Central Courtyard Area Hardscape and Softscape work completed
Nov 2025
Structure completed
Oct 2025
East Wing
Oct 2025
South Wing
Oct 2025
West Wing
Oct 2025
East ,South and West wing External Painting works in progress
Oct 2025
South face road and car parking area WIP
Oct 2025
West side driveway and car parking area WIP
Oct 2025
Basement Painting and Services work is completed
Oct 2025
Terrace Clay Tile Fixing Work Is Completed
Oct 2025
Tiling Work In Progress
Oct 2025
Painting work in progress
Oct 2025
Windows and Doors fixing work
Oct 2025
Finishing Work in Progress
Oct 2025
STP HVAC duct and Plumbing Work is completed
Oct 2025
Staircase Painting WIP
Oct 2025
PHE shaft door
Oct 2025
Corridor light fixing and Painting in progress
Oct 2025
Lift wall Texture completed
Oct 2025
Corridor certification in progress
Oct 2025
Corridor signage fixing is completed
Oct 2025
Ground floor triple height lobby finishing work in progress
Oct 2025
Ground floor corridor Painting work in progress
Oct 2025
East face( between E and D tower) driveway and car parking work is completed
Oct 2025
Podium Central Courtyard Area Hardscape and Softscape Work in progress
Oct 2025
Kids play area flooring and play area equipment work is completed
Oct 2025
Podium Central Courtyard Area Hardscape and Softs cape work in progress
Oct 2025