Overall View - Structure 530/530 Flats completed
May 2025

DRAG
East Wing
May 2025
South Wing
May 2025
West Wing
May 2025
East, South and West wing External Painting works Started
May 2025
Basement Painting and Services WIP
May 2025
Terrace Waterproofing Works is completed
May 2025
Terrace clay tile fixing work completed
May 2025
Tiling Work In Progress (530/530 Flats Completed)
May 2025
Painting work in progress (530/530 Flats primer completed)
May 2025
Windows and Doors fixing work is completed
May 2025
Finishing Work in Progress. QA Certification – 374/530 completed
May 2025
STP HVAC duct and Plumbing Work is in progress
May 2025
Staircase Painting WIP
May 2025
PHE shaft door fixing is completed
May 2025
Corridor light fixing and Painting WIP
May 2025
Lift wall Texture WIP
May 2025
East face( between E and D tower) driveway and car parking work is completed
May 2025
Podium Central Courtyard Area Hardscape and Softscape WIP
May 2025
Podium Central Courtyard Area Hardscape and Softs cape WIP
May 2025
Structure -530/530 Flats completed
Apr 2025
East Wing
Apr 2025
South Wing
Apr 2025
West Wing
Apr 2025
East, South and West wing External Painting works Started
Apr 2025
Basement Painting and Services WIP
Apr 2025
Terrace Waterproofing Works is completed
Apr 2025
Terrace clay tile fixing work is completed
Apr 2025
Tiling Work In Progress (530/530 Flats Completed)
Apr 2025
Painting work in progress (530/530 Flats primer completed)
Apr 2025
Windows and Doors fixing work is completed
Apr 2025
Finishing Work in Progress. QA Certification – 324/530 completed
Apr 2025
STP HVAC duct and Plumbing Work is in progress
Apr 2025
Corridor and Staircase Flooring and Painting Completed
Apr 2025
PHE shaft door fixing is completed
Apr 2025
East face( between E and D tower) driveway and car parking work is completed
Apr 2025
Podium Central Courtyard Area Hardscape and Softscape WIP
Apr 2025
Podium Central Courtyard Area Hardscape and Softs cape WIP
Apr 2025
Overall View - Structure -530/530 Flats completed
Mar 2025