Overall View - Structure completed
Aug 2025

DRAG
East Wing
Aug 2025
South Wing
Aug 2025
West Wing
Aug 2025
East ,South and West wing External Painting works in progress
Aug 2025
Basement Painting and Services work is completed
Aug 2025
Terrace Waterproofing Works is completed
Aug 2025
Terrace clay tile fixing work is completed
Aug 2025
Tiling Work In Progress
Aug 2025
Painting work in progress
Aug 2025
Windows and Doors fixing work is completed
Aug 2025
QA Certification in progress
Aug 2025
STP HVAC duct and Plumbing Work is in progress
Aug 2025
Staircase Painting WIP
Aug 2025
PHE shaft door fixing is completed
Aug 2025
Corridor light fixing and Painting WIP
Aug 2025
Lift wall Texture WIP
Aug 2025
Corridor certification in progress
Aug 2025
Corridor signage fixing is in progress
Aug 2025
Ground floor triple height lobby finishing WIP
Aug 2025
Ground floor corridor Painting WIP
Aug 2025
East face( between E and D tower) driveway and car parking work is completed
Aug 2025
Podium Central Courtyard Area Hardscape and Softscape WIP
Aug 2025
Podium Central Courtyard Area Hardscape and Softs cape WIP
Aug 2025
Emerald Overall View - Structure completed
Jul 2025
Emerald East Wing
Jul 2025
Emerald South Wing
Jul 2025
Emerald West Wing
Jul 2025
Emerald East, South and West wing External Painting works Started
Jul 2025
Emerald Finishing Works completed. QA Certification is in progress
Jul 2025
Emerald Lift wall Texture WIP
Jul 2025
Emerald Corridor Painting & QA Certification WIP
Jul 2025
Emerald Basement Painting and Services WIP
Jul 2025
Emerald Ground floor triple height lobby finishing WIP
Jul 2025
Emerald Ground floor corridor Painting WIP
Jul 2025
Emerald Terrace Clay Tile Fixing work is completed
Jul 2025
Emerald STP HVAC duct and Plumbing Work is in progress
Jul 2025
Emerald Staircase Painting WIP
Jul 2025
Emerald East face( between E and D tower) driveway and car parking work is completed
Jul 2025
Emerald Podium Central Courtyard Area Hardscape and Softscape WIP
Jul 2025
Emerald Podium Central Courtyard Area Hardscape and Softs cape WIP
Jul 2025
Emerald Overall View
Jun 2025
Emerald East Wing
Jun 2025
Emerald South Wing
Jun 2025
Emerald West Wing
Jun 2025
Emerald East, South and West wing External Painting works Started
Jun 2025
Emerald Basement Painting and Services WIP
Jun 2025
Emerald Terrace Waterproofing Works is completed
Jun 2025
Emerald Terrace Clay Tile Fixing Work is Completed
Jun 2025
Emerald Tiling Work in Progress
Jun 2025
Emerald Painting work in progress
Jun 2025
Emerald Windows and Doors fixing work is completed
Jun 2025
Emerald Finishing Work in Progress
Jun 2025
Emerald STP HVAC duct and Plumbing Work is in progress
Jun 2025
Emerald Staircase Painting WIP
Jun 2025
Emerald PHE shaft door fixing is completed
Jun 2025
Emerald Corridor light fixing and Painting WIP
Jun 2025
Emerald Lift wall Texture WIP
Jun 2025
Emerald Ground floor triple height lobby finishing WIP
Jun 2025
Emerald Ground floor corridor Painting WIP
Jun 2025
Emerald East face (between E and D tower) driveway and car parking work is completed
Jun 2025
Emerald Podium Central Courtyard Area Hardscape and Softscape WIP
Jun 2025
Emerald Podium Central Courtyard Area Hardscape and Softs cape WIP
Jun 2025