Mass excavation and Tower area Raft | Nearing Completion
Nov 2025

DRAG
WING A - Ground floor to First floor column shuttering in progress
Nov 2025
WING B – First floor slab shuttering in progress
Nov 2025
WING C – Ground floor to first floor column shuttering and First floor slab shuttering in progress progress
Nov 2025
Excavation and the Tower Area Foundation is in progress
Oct 2025
WING A - Ground floor to First floor column shuttering in progress
Oct 2025
WING B - Ground floor to First floor column shuttering in progress
Oct 2025
WING C – Ground floor to first floor column shuttering in progress
Oct 2025
Mass excavation - 95% work completed, Tower area Raft – 95% completed, Hospital area raft – 100% work completed
Sep 2025
WING A - Ground floor Slab shuttering in progress
Sep 2025
WING B - Ground floor slab shuttering work in progress
Sep 2025
WING C - Ground floor Slab shuttering in progress
Sep 2025
Hospital block - Basement 2 slab reinforcement work in progress
Sep 2025