Excavation and the Tower Area Foundation is in progress
Oct 2025

DRAG
WING A - Ground floor to First floor column shuttering in progress
Oct 2025
WING B - Ground floor to First floor column shuttering in progress
Oct 2025
WING C – Ground floor to first floor column shuttering in progress
Oct 2025
Mass excavation - 95% work completed, Tower area Raft – 95% completed, Hospital area raft – 100% work completed
Sep 2025
WING A - Ground floor Slab shuttering in progress
Sep 2025
WING B - Ground floor slab shuttering work in progress
Sep 2025
WING C - Ground floor Slab shuttering in progress
Sep 2025
Hospital block - Basement 2 slab reinforcement work in progress
Sep 2025
Beryl Mass excavation - work is in progress
Aug 2025
Beryl Wing A - Ground floor column shuttering in progress
Aug 2025
Beryl Wing B - Upper basement 1 slab shuttering in progress
Aug 2025
Beryl Wing C - Upper Basement 1 Slab shuttering in progress
Aug 2025
Beryl Hospital block –raft concreting in progress. Basement 2 – Slab shuttering in progress
Aug 2025