Beryl Mass excavation - work is in progress
Aug 2025

DRAG
Beryl Wing A - Ground floor column shuttering in progress
Aug 2025
Beryl Wing B - Upper basement 1 slab shuttering in progress
Aug 2025
Beryl Wing C - Upper Basement 1 Slab shuttering in progress
Aug 2025
Beryl Hospital block –raft concreting in progress. Basement 2 – Slab shuttering in progress
Aug 2025
EL Dorado Beryl - Mass excavation (90% work completed). Tower area Raft (100% work completed)
Jul 2025
EL Dorado Beryl Wing A - Upper basement 2 slab shuttering in progress
Jul 2025
EL Dorado Beryl Wing B - Lower basement completed and column concreting in progress for upper basement 2
Jul 2025
EL Dorado Beryl Wing C - Lower basement slab work is underway
Jul 2025
EL Dorado Beryl Hospital Block – Raft concreting work is underway
Jul 2025
EL Dorado Beryl Wing B – Milestone Release On Casting of Footing/Raft - Status as on 24th July 2025
Jul 2025