B block wing A - First floor walk slab shuttering work in progress
Feb 2026

DRAG
wing B - Second floor beam shuttering work in progress.
Feb 2026
B block wing C - First floor slab shuttering work in progress.
Feb 2026
B block South ramp B3 - B2 ramp completed.
Feb 2026
Hospital-
3)Pour3 - Ground floor slab shuttering wip.
4)Pour4 - Ground floor slab shuttering wip.
Feb 2026
Wing B - Milestone Release - On Casting of First floor slab - Status as on 02nd March 2026
Mar 2026
WING A - First floor slab concreting in progress
Jan 2026
WING B - First floor slab shuttering in progress
Jan 2026
WING C - first floor slab shuttering in progress
Jan 2026
Wing A - Milestone Release - On Casting of First Floor Slab - Status as on 31st January 2026
Jan 2026