Structure - 525/525 Flats Casted
Nov 2025

DRAG
Wing A – Terrace Floor slab completed
Nov 2025
Wing B – Terrace Floor slab completed
Nov 2025
Wing C - Terrace Floor slab completed
Nov 2025
Podium Central Courtyard area Waterproofing works in progress
Nov 2025
Toilet Waterproofing works in progress
Nov 2025
Internal flats punning work in progress
Nov 2025
Internal flats Tiling work in progress
Nov 2025
Internal flats Painting Work in progress
Nov 2025
Internal flats QA certification work in progress
Nov 2025
Corridor Gypsum Punning and Painting works in progress
Nov 2025
Corridor Area Tiling works started
Nov 2025
Wing C - Milestone Release - On Casting of terrace slab - Status as on 02.12.2025
Dec 2025
Wing B - Milestone Release - On Casting of terrace slab - Status as on 01.12.2025
Dec 2025
Wing C - Milestone Release - On commencement of Flooring 14th Floor - 22nd Floor - Status as on 26th Nov 2025
Nov 2025
Wing C - Milestone Release - On commencement of Flooring 14th Floor - 22nd Floor - Status as on 26th Nov 2025
Nov 2025
Wing A - Milestone Release - On casting of Terrace slab - Status as on 15th Nov 2025
Nov 2025
Wing A - Milestone Release - On commencement of installation of lifts - Status as on 14th Nov 2025
Nov 2025
Dioro
Oct 2025
Wing A – Terrace Floor slab shuttering WIP
Oct 2025
Wing B – 21st and 22nd Floor slab shuttering in progress
Oct 2025
Wing C- Terrace Floor slab shuttering WIP
Oct 2025
Podium Central Courtyard area Waterproofing works started
Oct 2025
Toilet Waterproofing works in progress
Oct 2025
Internal Flats punning work in progress
Oct 2025
Internal flats Tiling in progress
Oct 2025
Internal flats Painting Work in progress
Oct 2025
Internal flats QA certification Work is in progress
Oct 2025
Corridor Painting works in progress
Oct 2025
Basement Concrete flooring works in progress
Oct 2025
Dioro
Sep 2025
Wing A - 21st Floor slab shuttering WIP
Sep 2025
Wing B - 20th Floor slab shuttering in progress
Sep 2025
Wing C - 22nd Floor slab shuttering WIP
Sep 2025
Podium Central Courtyard area Waterproofing works started
Sep 2025
Toilet Waterproofing works in progress
Sep 2025
Internal flats plastering work in progress
Sep 2025
Internal flats Tiling work in progress
Sep 2025
Internal flats Painting in progress
Sep 2025
Corridor Gypsum Plastering and Painting work has just begun
Sep 2025
Basement Concrete flooring works in progress
Sep 2025