Wing A – Terrace Floor slab completed
Feb 2026

DRAG
Wing B - Terrace Floor slab completed
Feb 2026
Wing C - Terrace Floor slab completed
Feb 2026
Terrace waterproofing and Terrace Tiling WIP
Feb 2026
Toilet Waterproofing works in progress
Feb 2026
Internal flats Gypsum punning work in progress
Feb 2026
Internal flats Tiling work in progress
Feb 2026
Internal flats painting Work in progress
Feb 2026
Internal flats QA certification Work is in progress
Feb 2026
Corridor Gypsum Painting works in progress
Feb 2026
Corridor Area Tiling works work in progress
Feb 2026
Lift Installation work in progress
Feb 2026
External Painting work started
Feb 2026
Dioro
Jan 2026
Wing A – Terrace Floor slab completed
Jan 2026
Wing B – Terrace Floor slab completed
Jan 2026
Wing A - Terrace Floor slab completed
Jan 2026
Terrace waterproofing and finishing WIP
Jan 2026
Toilet Waterproofing works in progress
Jan 2026
Plastering work in progress
Jan 2026
Tiling work in progress
Jan 2026
Internal flats Work in progress
Jan 2026
Finishing work
Jan 2026
Corridor Painting works in progress
Jan 2026
Corridor Area Tiling work in progress
Jan 2026
Lift Installation work in progress
Jan 2026
External Painting work
Jan 2026