Wing A - Milestone Release On casting of Fifth floor slab - Status as on 31st Oct 2025
Oct 2025

DRAG
Wing A - Milestone Release On casting of Fifth floor slab - Status as on 31st Oct 2025
Oct 2025
OVERALL VIEW – 1.Wing A&B – 4th and 5th floor slab shuttering WIP
2. Wing – C – 3rd floor slab completed
Sep 2025
Wing A - 5th floor slab shuttering in progress
Sep 2025
Wing B – 4th floor slab shuttering WIP, Entrance area canopy ready for concrete
Sep 2025
Wing C -3rd floor slab concrete completed, Non tower Area Upper basement and Ground floor slab shuttering WIP
Sep 2025
STP –Wall concrete in progress
Sep 2025
El Dorado Cobalt Structure- 68/948 flats Casted. Overall view - Wings A & B – 3rd and 4th floor slab shuttering WIP. Wing C- 2nd and 3rd floor initial setting WIP
Aug 2025
El Dorado Cobalt Wing A – 3rd and 4th floor slab shuttering in progress
Aug 2025
El Dorado Cobalt Wing B – 2nd and 3rd floor slab shuttering WIP
Aug 2025
El Dorado Cobalt Wing B & C – 3rd and 4th floor slab shuttering WIP
Aug 2025
El Dorado Cobalt STP – Wall concrete in progress
Aug 2025
Cobalt Structure - 26/948 flats Casted. Overall View - Wings A & B – 2nd and 3rd floor slab shuttering WIP.. Wing C – 1st and 2nd floor initial setting WIP
Jul 2025
Wing A – 2nd and 3rd floor slab shuttering in progress
Jul 2025
Wing B – Second floor slab aluminium shuttering WIP
Jul 2025
Wing C – 1st and 2nd floor Aluminum initial setting WIP
Jul 2025
STP – Wall concrete in progress
Jul 2025