OVERALL VIEW – 1.Wing A&C – 6th and 5th floor slab shuttering WIP 2. Wing – C – 3rd ,4th and 5th floor slab shuttering WIP
Oct 2025

DRAG
Wing A – 6th floor slab shuttering in progress
Oct 2025
Wing B – 3rd ,4th & 5th floor slab shuttering WIP
Oct 2025
Wing C -5th floor slab shuttering WIP,
Non tower Area Upper basement and Ground floor slab shuttering WIP
Oct 2025
STP structure work in progress
Non tower Area Upper basement slab shuttering WIP
Oct 2025
Wing A - Milestone Release On casting of Fifth floor slab - Status as on 31st Oct 2025
Oct 2025
Wing A - Milestone Release On casting of Fifth floor slab - Status as on 31st Oct 2025
Oct 2025
OVERALL VIEW – 1.Wing A&B – 4th and 5th floor slab shuttering WIP
2. Wing – C – 3rd floor slab completed
Sep 2025
Wing A - 5th floor slab shuttering in progress
Sep 2025
Wing B – 4th floor slab shuttering WIP, Entrance area canopy ready for concrete
Sep 2025
Wing C -3rd floor slab concrete completed, Non tower Area Upper basement and Ground floor slab shuttering WIP
Sep 2025
STP –Wall concrete in progress
Sep 2025
El Dorado Cobalt Structure- 68/948 flats Casted. Overall view - Wings A & B – 3rd and 4th floor slab shuttering WIP. Wing C- 2nd and 3rd floor initial setting WIP
Aug 2025
El Dorado Cobalt Wing A – 3rd and 4th floor slab shuttering in progress
Aug 2025
El Dorado Cobalt Wing B – 2nd and 3rd floor slab shuttering WIP
Aug 2025
El Dorado Cobalt Wing B & C – 3rd and 4th floor slab shuttering WIP
Aug 2025
El Dorado Cobalt STP – Wall concrete in progress
Aug 2025