Cobalt Overall View. Wings A & B – Second floor slab Aluminium initial setting WIP. Wing C – First floor Slab 50% completed
Jun 2025

DRAG
Cobalt Wing A – Second floor slab shuttering in progress
Jun 2025
Cobalt Wing B - Second floor slab aluminium shuttering WIP. Wing C – First floor slab Aluminium
Jun 2025
Cobalt STP – Raft completed, Wall concrete in progress
Jun 2025
Overall view
May 2025
Wing A – First floor 2 flats (ZS,ZR) Aluminium initial setting WIP
May 2025
Wing B - Ground floor (S & Q unit) concrete completed, Wing C(M & K unit) – Aluminium initial setting in progress
May 2025
STP – Raft completed, wall reinforcement and concrete in progress
May 2025
Overall view. Wings A&B – First floor slab concrete completed and First floor 2 flats Aluminium initial setting WIP. Wing C – GF Slab completed, 2 Flats initial setting WIP
Apr 2025
Wing A – First floor flats Aluminium initial setting WIP
Apr 2025
Wing B – 50% First floor slab completed remaining 50% slab reinforcement WIP
Apr 2025
Wing C – GF 2 flats Aluminium Initial setting WIP. Balance 50% First floor slab (Conventional Area)shuttering and reinforcement WIP
Apr 2025
Ground floor Wing B – (S & Q unit), Wing C –(M & K unit) Aluminium shuttering works started
Apr 2025