COBALT - Wing A
Oct 2026

DRAG
COBALT - Wing A
Oct 2026
Cobalt Wing B - Milestone Release - "On Casting of terrace slab" - Status as on 27th
Oct 2026
Cobalt Wing A - Milestone Release -"On commencement of window fixing -7F-13F" Status as on 27th
Oct 2026
Lower basement flooring and painting work in progress
Sep 2026
Internal certification is in progress
Sep 2026
Internal certification is in progress
Sep 2026
Internal certification is in progress
Sep 2026
painting work in progress
Sep 2026
UPVC windows fixing work in progress
Sep 2026
UPVC windows fixing work in progress
Sep 2026
Plastering and flooring work in progress
Sep 2026
Wing C – Above terrace works in progress
Sep 2026
Wing B – Terrace slab shuttering and above terrace works in progress
Sep 2026
Wing A – Above terrace works in progress
Sep 2026
OVERALL VIEW – 1.Wing A – Above terrace works in progress
2. Wing B –Terrace slab shuttering and Above terrace works in progress
3. Wing C –Above terrace works in progress
Sep 2026
Wing A - Milestone Release on Casting of Terrace floor slab on 21.09.2026
Sep 2026
Wing B - Milestone Release on Casting of Twenty first floor slab on 21.09.2026
Sep 2026
Wing C - Milestone Release On Casting of Terrace floor slab
Sep 2026
Overall View - Wing A - Terrace slab shuttering WIP, Wing B - 20th and terrace slab shuttering WIP
Aug 2026
Wing A - Terrace slab shuttering in progress
Aug 2026
Wing B - 20th and terrace slab shuttering WIP
Aug 2026
Wing C - Terrace slab completed
Aug 2026
Internal plastering and flooring work in progress
Aug 2026
Windows fixing work in progress
Aug 2026
Painting work in progress
Aug 2026
Internal certification in progress
Aug 2026
Lower basement flooring and painting work in progress
Aug 2026
Wing B - Milestone release - On casting of Eighteenth floor slab - Status as on 18th Aug 2026
Aug 2026